Warringah Mall Zone 2 Civil Works

ClientScentre Design and Construction Pty Ltd
LocationWarringah NSW
Value$1.1 million
StartMarch 2016
Duration12 weeks

Scope

This project involved the demolition, regrading and resheeting of approxiamtely 8500m2 of asphalt carpark, the reconstruction of roundabouts in Green Street and Cross Street, and the associated external civil works including the installation of new stormwater lines and pits, footpaths and kerb ramps.